Illustration of ‘Lack of communication, coordination’ problem

Naiyaca Campus: A $40 Million Vision or a Construction Nightmare?

Spread the love

Last week, we reported on the Naiyaca Campus, a $40 million initiative aimed at providing an affordable tertiary education option for students in Fiji’s Northern Division through the Fiji National University (FNU). While construction began in 2018, momentum significantly declined and ultimately ceased in 2020, leaving only rusty iron frameworks as evidence of the project.

The Naiyaca Campus was meant to enhance educational accessibility in the region. Initially, FNU announced Civil and Environmental Engineering Solutions Ltd. (CEESOL) as the main contractor, with support from Design Hut, Edison Consultants, and Quantech Pacific. The campus was strategically located near the Labasa Town Centre for better public transport access.

The project, funded by the government, started civil works in 2015, which included foundational preparations. However, difficulties emerged in coordinating designs and managing construction processes. A contractor, speaking anonymously, revealed that CEESOL was responsible for overseeing the project, yet various design and structural issues delayed construction significantly.

Confusion over design instructions led to disagreements on fundamental aspects, such as ground floor elevation. The contractor emphasized that miscommunication between the involved parties, especially regarding drawing coordination, played a critical role in the delays. Instability regarding the decisions between FNU and the Fiji Roads Authority on the site’s infrastructure further hindered progress.

Despite these setbacks, it is crucial to recognize that addressing these coordination and communication challenges could lead to future improvements in project management in similar undertakings. By learning from the flaws pointed out during the Naiyaca Campus project, stakeholders can enhance collaboration and communication skills, crucial components for successful project completions in the construction sector.

In summary, the Naiyaca Campus project serves as a warning on the importance of effective communication and coordination among contractors, architects, and consultants. While currently stalled, there remains hope that these lessons will contribute positively to streamlined future projects, ultimately benefiting educational access in Fiji.